Construction Contracts

Construction Dispute Resolution Methods Explained

Construction dispute resolution covers the ways the parties to a construction project settle disagreements they cannot resolve themselves. Disputes are common in construction. Projects are complex and long, involve many parties and carry a great deal of risk, so disagreements over payment, variations, delay and defects are almost inevitable. What matters is how quickly and economically they are resolved, and whether the project and working relationships survive the process.

This guide explains why disputes arise and how to prevent them. It describes each main method of resolution, from negotiation to litigation, and compares them. It then explains how disputes are handled under JCT, NEC4 and FIDIC, and the part the quantity surveyor plays. It is general information for construction professionals, not legal advice. Specialist legal advice should always be taken on a live dispute.

Why Construction Disputes Arise

Most construction disputes fall into a few familiar categories.

  • Payment. Disagreements over interim payments, retention, set-off and the final account.
  • Change. Whether an instruction is a variation or compensation event, and what it is worth.
  • Delay and disruption. Who caused delay, whether an extension of time is due, and whether loss and expense or delay damages follow.
  • Defects and quality. Whether work meets the specification, and who pays to put it right.
  • The contract itself. Ambiguous drafting, conflicting documents, or bespoke amendments that change the standard risk balance.

It also helps to distinguish a claim from a dispute. A claim is a request for more time or money under the contract. It only becomes a dispute when it is rejected, or not answered, and the parties cannot agree. Many disputes can be avoided by dealing with claims promptly and fairly.

Preventing Disputes

The best dispute resolution is avoiding the dispute in the first place. Good practice includes clear tender and contract documents, a realistic programme and budget, and prompt administration of the contract. That means giving notices on time, valuing change quickly and keeping good records.

NEC4’s early warnings and compensation event time limits are designed to deal with problems as they arise, rather than leaving them to the end of the job. JCT 2024 encourages early notification and negotiation of disputes too. Our guides to valuing variations and compensation events and construction programmes explain how timely change and delay management reduces disputes.

Construction Dispute Resolution Methods

Select a method to see how it works, its strengths and its limits.

Negotiation

The parties discuss the dispute directly, without a third party, and try to agree a settlement. Negotiation is quick, cheap and private, and the parties keep full control of the outcome. Most construction disagreements are settled this way.

Many contracts make negotiation a formal first step. For example, NEC4 includes a stage where senior representatives of each party try to resolve the dispute before it goes further. Negotiations are often held on a “without prejudice” basis, so that offers cannot later be used as evidence. The QS often leads the commercial side of negotiations, particularly on the value of variations and the final account.

Mediation

An independent mediator helps the parties negotiate a settlement. The mediator does not decide the dispute. They help each side understand the other’s position, test the strengths and weaknesses of their case and explore options. Mediation is confidential and without prejudice, and the parties sign a mediation agreement setting out the terms.

Mediation can be arranged quickly and often takes only a day or two. Any settlement is recorded in a binding agreement. It suits disputes where the parties want to preserve their relationship, or where the cost of a formal process would be out of proportion to the sums at stake.

The courts now strongly encourage mediation and other ADR. Following the Court of Appeal’s decision in Churchill v Merthyr Tydfil County Borough Council (2023), and amendments to the Civil Procedure Rules from 1 October 2024, the courts in England and Wales can order parties to take part in ADR. They can also take an unreasonable refusal into account when deciding who pays the costs.

Adjudication

Under the Housing Grants, Construction and Regeneration Act 1996, as amended, a party to a construction contract has a statutory right to refer a dispute to adjudication at any time. An independent adjudicator decides the dispute quickly. The usual timetable is as follows.

  • A notice of adjudication is served, and an adjudicator is appointed.
  • The referral is served within 7 days of the notice.
  • The adjudicator reaches a decision within 28 days of the referral. This can be extended by 14 days with the referring party’s consent, or longer if both parties agree.

The adjudicator’s decision is binding and must be complied with. If necessary, it can be enforced through the courts, which usually do so quickly. But it is only temporarily binding. Either party can later have the dispute finally decided by litigation or arbitration, or the parties can settle it by agreement. In the meantime, the decision stands. That “pay now, argue later” principle keeps cash moving during the project.

Some points for QSs to note:

  • The statutory right does not apply to every contract. Contracts with residential occupiers, and some process plant and other excluded operations, fall outside the Act.
  • Each party usually bears its own costs, so even a successful party rarely recovers the cost of an adjudication.
  • Where a payer has failed to give a valid payment or pay less notice, the notified sum must be paid. The payer generally has to pay it before it can start a separate adjudication about the true value of the work.

Adjudication was meant to be informal, but larger adjudications now often involve detailed submissions and expert reports.

Expert Determination

The parties agree to appoint an independent expert, such as a QS, engineer or accountant, to decide a specific issue. It suits disputes about valuation, measurement or technical matters, such as the value of a final account or whether a plant meets its performance tests.

Expert determination is usually quick and private. It depends entirely on the parties’ agreement, which sets out the procedure. The expert’s decision is normally final and binding, with very limited grounds of challenge, for example where the expert has not answered the question they were asked. That finality is both its strength and its risk. The IChemE forms of contract make particular use of experts for technical disputes, as our guide to IChemE forms of contract explains.

Dispute Boards

A dispute board is a panel, usually of one or three independent experts, appointed at the start of a project. It stays involved throughout, visiting site, keeping up to date with progress and helping the parties deal with issues before they become disputes. Dispute boards are common on large infrastructure and international projects.

Their status varies between contracts. Under FIDIC’s 2017 editions, the Dispute Avoidance/Adjudication Board (DAAB) gives informal assistance and also makes decisions that are binding unless and until they are revised by agreement or arbitration. Under NEC4, Option W3 provides a Dispute Avoidance Board that makes recommendations, with a tribunal deciding the dispute if a recommendation is not accepted.

Arbitration

Arbitration is a private, binding alternative to the courts. It only applies if the parties have agreed to it in writing, usually through an arbitration clause in the contract. One or more arbitrators, often with construction expertise, hear the evidence and make a final award.

Arbitration is confidential, which matters to many parties. Awards are final, with very limited rights of appeal, and they can be enforced internationally under the New York Convention. That is why arbitration is standard on international projects and under FIDIC. It can, however, be as slow and expensive as litigation on complex disputes.

In England and Wales, arbitration is governed by the Arbitration Act 1996, as updated by the Arbitration Act 2025, which came into force on 1 August 2025. The 2025 Act clarified the law governing arbitration agreements, set out a statutory duty for arbitrators to disclose possible conflicts of interest and gave arbitrators a power to decide issues summarily.

Litigation in the Technology and Construction Court

Where the contract does not provide for arbitration, final resolution is through the courts. In England and Wales, most significant construction disputes are heard in the Technology and Construction Court (TCC), a specialist court within the Business and Property Courts. The TCC also enforces adjudication decisions.

Before issuing a claim, parties must normally follow the Pre-Action Protocol for Construction and Engineering Disputes. The claimant sends a letter of claim setting out its case. The defendant responds, usually within 28 days, and the parties meet to try to resolve or narrow the issues. Failing to follow the protocol can lead to costs penalties.

Litigation produces a binding, public judgment, with rights of appeal. It is usually the slowest and most expensive route, and the courts now expect parties to have considered ADR first.

Small Claims

In England and Wales, most claims worth up to £10,000 are dealt with on the small claims track of the County Court. The process is simpler and cheaper, and parties often represent themselves. It suits small domestic and trade disputes, but is rarely relevant to commercial construction projects.

Comparing Construction Dispute Resolution Methods

MethodOutcomeTypical TimescalePrivate?Relative CostBest For
NegotiationAgreement between the partiesDays to weeksYesLowMost disagreements, as a first step
MediationSettlement agreement, if reachedOften one or two days, once arrangedYesLow to moderatePreserving relationships and avoiding formal costs
AdjudicationDecision binding until finally decided28 days from referral, extendableGenerally yesModeratePayment, valuation and delay disputes during a project
Expert determinationUsually final and bindingWeeks to monthsYesModerateSpecific valuation or technical questions
Dispute boardRecommendation or interim binding decision, depending on the contractOngoing through the projectYesModerate, but ongoingLarge and long projects
ArbitrationFinal awardMonths to yearsYesHighInternational and confidential disputes
Litigation (TCC)Final public judgmentMonths to yearsNoHighComplex disputes, points of law and multi-party claims

Dispute Resolution Under JCT, NEC4 and FIDIC

JCT. JCT contracts provide for adjudication under the Construction Act, optional mediation and final resolution by either arbitration or litigation, as chosen in the Contract Particulars. If arbitration is not selected, litigation applies. The 2024 Edition places more emphasis on notifying and negotiating disputes early.

NEC4. Disputes are dealt with under Option W1 or W2, or Option W3. W1 is used where the Construction Act does not apply and W2 where it does, and both lead to adjudication. W3 uses a Dispute Avoidance Board. NEC4 adds a step where senior representatives try to resolve the dispute first. Final resolution is by the tribunal named in the contract, either arbitration or the courts.

FIDIC. Under the 2017 editions, disputes go first to the standing DAAB, then to a period of amicable settlement, and finally to international arbitration, usually under the ICC Rules.

Our overview of NEC, JCT and FIDIC contracts and our guide to JCT vs NEC contract administration explain the wider differences between the forms.

Choosing the Right Method

Check the contract first. Many contracts set out a required process, and the statutory right to adjudicate applies to most construction contracts regardless.

Consider the type of dispute. A specific technical or valuation question may suit expert determination. A payment dispute during the project often suits adjudication. A complex dispute involving points of law or several parties may need arbitration or litigation.

Weigh time and cost against the sums at stake. A formal process can quickly cost more than the amount in dispute. Mediation or negotiation is often the most economical route.

Think about the relationship. If the parties must keep working together, less adversarial methods are usually better.

Consider confidentiality and enforcement. Arbitration and mediation are private, and arbitration awards are enforceable internationally. Court judgments are public.

Remember the courts expect ADR. Unreasonably refusing to mediate or negotiate can lead to costs penalties, and the courts can now order parties to try ADR.

The QS’s Role in Construction Disputes

Quantity surveyors are involved in disputes at every stage.

  • Avoiding disputes. Valuing change promptly and fairly, giving and responding to notices on time and keeping clear records.
  • Preparing and assessing claims. Quantifying variations, loss and expense, compensation events and the final account, with clear evidence for every figure.
  • Supporting negotiation and mediation. Testing the value of each side’s position, and identifying where a settlement makes commercial sense.
  • Acting in adjudication and arbitration. Preparing the quantum (the financial value) of the case, often working with lawyers and delay experts.
  • Acting as an expert witness. Giving independent opinion evidence on quantum. An expert witness owes their duty to the tribunal, not to the party paying them. They must follow the relevant rules, such as Part 35 of the Civil Procedure Rules, and the RICS practice statement for surveyors acting as expert witnesses.

Records win disputes. Dated records, programmes, photographs, instructions and cost data made at the time carry far more weight than reconstructions made later. Our guide to construction data management explains which records to keep and for how long. Disputes over the final figures are covered in our guide to final accounts and settlement. Dispute resolution is also one of the main quantity surveyor career paths.

Conclusion

Construction dispute resolution offers a range of methods, from informal negotiation to a final court judgment. Each has its place. Negotiation and mediation are quick, cheap and private. Adjudication keeps cash flowing during the project with a fast, temporarily binding decision. Expert determination suits specific technical and valuation questions. Arbitration and litigation give a final answer on the largest and most complex disputes, at greater cost.

The most effective approach is to prevent disputes in the first place, through clear contracts, prompt administration and good records. When a dispute does arise, choosing the right method, at the right time, and supporting it with clear evidence makes all the difference. The QS plays a central part in all of this, from valuing change on day one to giving expert evidence on quantum if a dispute reaches a tribunal.